Deep Drawn Stamping of Steel Bracket Mount for the Appliance IndustryRecently, our client contacted Perfection Spring & Stamping Corp. when looking for an inexpensive solution for a secondary deburring operation that needed to be performed on a large series of shallow drawn shells. Using Deep Drawn progressive stamping technology, we were producing massive volumes of this part for our customer. These components were then meant to be encapsulated in plastic, a process that was carried out by this client. However, the shells contained sharp edges which caused an unanticipated safety concern. Given the massive quantity of shallow drawn shells that was being manufactured, adding a secondary deburring process would exceed one million dollars in additional fees over the remaining life of the program. Unable to meet this unexpected expense, our client requested that we find a more cost-effective solution to their problem. Dedicated to helping our buyer, Perfection Spring & Stamping Corp. found a way to automate a deburring operation into the primary manufacturing process. The final result was a clean part, free of all burrs and sharp edges. Moreover, as this process was to be performed concurrently with all primary operations, there would be no additional manufacturing expenditures. By coming up with this innovative and cost-effective solution, Perfection Spring & Stamping Corp. was able to provide parts that fulfilled all of our client's safety requirements at no additional charge. This innovative solution saved our client over one million dollars in unexpected manufacturing fees!
Deep Drawn Steel Bracket Mount Project Highlights
Product Description |
This Steel Bracket Mount is used within a clothes dryer application |
Capabilities Applied/Processes |
Deep Drawn Progressive Stamping
Deburring
- Deburring Operation is Automated and Part of the Primary Manufacturing Process for a Cost Effective Solution
|
Equipment Used to Manufacture Part |
Minster Press
Progressive Die Tooling w/ Coining Station |
Overall Part Dimensions |
Material Thickness: .022"
Length: 6.5" |
Width: 1.25"
Height: 1.00" |
|
Tightest Tolerances |
±.005" |
Material Used |
Electro-Galvanized Steel |
Features |
Burr-free Edge
Deburred Complete in Progressive Die |
In Process Testing/Inspection Performed |
In-Process Real-time SPC of Critical Dimensions
CMM Measurement
Micro Vue Vision Measurement
Salt Spray Testing
Dimensional Results Reporting
Control Plan |
Process Flow Diagram
Failure Mode and Effects Analysis (FMEA)
Gage Repeatability and Reproducibility Variable Data Report
Raw Material Chemical Composition Results
MSDS - Material Safety & Data Report / Substances and Materials |
|
Estimated Part Weight |
.15 lbs |
Industry for Use |
Appliance |
Volume |
2,400,000 Pieces |
Packaging |
Bulk Pack Corrugated Packaging |
Lead Time |
Tooling: 12 Weeks
Production Parts: 3 Weeks |
Delivery Location |
Ohio |
Standards Met |
Customer supplied print, 2D CAD Drawing |
Product Name |
Clothes Dryer Bracket Mount |